What a Septic Inspection Covers
Think of it in three stops: the tank, the box and the field.
At the tank, Rule .1006 has the inspector record its location and depth below finished grade, any access risers, the condition of the lids, baffle wall and outlet tee, the water level against the outlet, the outlet filter, roots, leakage, connections from downspouts or sump pumps that are not permitted, the last pumping date if known, and the percentage of solids.
At the distribution box, the inspector uncovers it to look, as Rule .1005 requires, unless there is another way to observe its condition. Any part where deterioration is suspected gets probed.
At the field, the record covers the type of field, the number and length of lines, evidence of past or current surfacing, traffic over it, and confirmation that effluent is reaching it. Vegetation, grading and drainage are noted for their effect on the system, a useful check where parts of town can flood.
Pump tanks, treatment units and control panels are on the Rule .1005 list as well. The paperwork bookends it all: a written contract and the owner's written permission before the visit, and a written report within 10 business days that names anything not inspected and the reason, signed with the inspector's license number, per Rule .1002.