What a Septic Inspection Covers
Under the board's Rule .1005, the inspection takes in every major part: septic tanks, pump tanks, distribution devices, dispersal fields, treatment units, control panels, any other component the permit requires including drainage, and the vegetation and grading that affect the system. The inspector opens the lids and distribution devices, unless they are blocked, and probes any part where deterioration is suspected.
Here is what gets written down, per Rule .1006.
At the tank, the inspector notes its distance from the house, from a well and from visible water lines, the depth from finished grade to the top of the tank or riser, and the condition of the lids, baffle wall and outlet tee. Water level against the outlet, roots, leakage, the outlet filter, non-permitted inflow from downspouts or sump pumps, and the share of solids all go in the report.
On a lot with its own well, the type of water supply is recorded too.
In the field, the inspector records the type of dispersal field, how many lines there are and how long, any past or current surfacing, signs of traffic, and whether effluent is reaching the field.
The client receives a written report within 10 business days, and Rule .1002 requires it to name what was not inspected and why. Failing to locate a component must be reported as "could not locate," which the rule says is not the same as "not visible."